Friday, November 2, 2018

Project Complete except for some minor landscaping on Carol Ln and Misc. striping

.Thank You for your patience throughout the project in your neighborhood 

Monday, October 29, 2018

Project Complete

.Thank You for your patience throughout the project in your neighborhood 

Thursday, October 11, 2018

Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·       Storm sewer work on Carol finished this week 
  • Curb work started this week
 
 
Work Anticipated the week of October 15th to October 19th

  • Finish curb removal and replacement on Carol 
  • Tentatively pavement milling is to start late in the week of October 15th

.Thank You for your patience as this work continues  in your neighborhood 










Friday, October 5, 2018

Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·       Storm sewer work on Carol started this week  and should be completed on weather permitting Monday or Tuesday next week .



 
Work Anticipated the week of October 8th to October 12th

  • Curb removal and replacement will begin the middle of next week on Carol.
  • Tentatively pavement milling is to start the week of October 15th
  • Final Round of Mars patching tentative for the week of October 15
.Thank You for your patience as this work continues  in your neighborhood 












Friday, September 21, 2018

Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Phase 2 is paved out

M.A.R.S. Patching is completed

 
Work Anticipated the week of September 24th to the 28th.

  • Carol Lane to Begin with Curb Remove and Replace as well as storm sewer work.
Thank You for your patience as this work continues in your neighborhood.






Saturday, September 15, 2018


Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Phase 2 is paved out

M.A.R.S. Patching is completed

 
Work Anticipated to be performed, September 17th to September 21st.
  • Misc. clean up and punch lists



Thank You for your patience during this construction season.
 

Sunday, September 9, 2018



Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Phase 2 is paved out

M.A.R.S. Patching is completed

 
Work Anticipated to be performed, September 10th to September 14th
  • Misc. clean up and punch lists



Thank You for your patience during this construction season.