Work Performed:
·
Completed concrete curb & gutter replacement
in Group 1
o Magnolia
Street
o Timbers
Edge Lane
o Merle
Lane
o Blake
Lane
o Leanne
Court
o Sioux
Trail
·
Performed concrete curb & gutter replacement
along one side of the street in Group 2, including:
o Lakewood
Lane (Greenwood Road to West End)
o Prairie
Lawn Road (Independence to Cul-de-Sac)
o Pfingsten
Road (Linneman Street to South End)
o Jerrie
Lane (Sherly Lane to Michael Manor)
o Spruce
Street (Robincrest Lane to Linneman Street)
o Larkdale
Drive (Spruce Street to 2121 Larkdale)
o Linden
Leaf Drive (Glenview Road to Roosevelt Avenue)
o Railroad
Avenue (Glenview Road to Linnman Street)
Work Anticipated to be performed, July 23rd to
July 27th
·
Complete Concrete curb & gutter on opposite
side of the street along Group 2 streets
·
Structure adjustments along Group 2 Streets
·
Pavement Removal / Milling along Group 1 Streets
Residents will be notified of any driveway restrictions
within Group 2.
A majority of the concrete work will be completed next week
within Group 2 streets. Work was performed on one side of the street last week,
with the other side of the street being performed next week.
All the concrete work along Group 1 streets is now
completed. We apologize for the delay, but needed to complete the storm sewer
improvements prior to the remaining concrete work being completed. Pavement
removal / surface grinding is anticipated to begin mid next week along Group 1
streets. If all goes as planned, asphalt surface paving will begin the week of
July 30th.
Thanks again for your patience as you are without driveway
access during concrete curb & gutter removal and replacement.