Friday, November 2, 2018

Project Complete except for some minor landscaping on Carol Ln and Misc. striping

.Thank You for your patience throughout the project in your neighborhood 

Monday, October 29, 2018

Project Complete

.Thank You for your patience throughout the project in your neighborhood 

Thursday, October 11, 2018

Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·       Storm sewer work on Carol finished this week 
  • Curb work started this week
 
 
Work Anticipated the week of October 15th to October 19th

  • Finish curb removal and replacement on Carol 
  • Tentatively pavement milling is to start late in the week of October 15th

.Thank You for your patience as this work continues  in your neighborhood 










Friday, October 5, 2018

Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·       Storm sewer work on Carol started this week  and should be completed on weather permitting Monday or Tuesday next week .



 
Work Anticipated the week of October 8th to October 12th

  • Curb removal and replacement will begin the middle of next week on Carol.
  • Tentatively pavement milling is to start the week of October 15th
  • Final Round of Mars patching tentative for the week of October 15
.Thank You for your patience as this work continues  in your neighborhood 












Friday, September 21, 2018

Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Phase 2 is paved out

M.A.R.S. Patching is completed

 
Work Anticipated the week of September 24th to the 28th.

  • Carol Lane to Begin with Curb Remove and Replace as well as storm sewer work.
Thank You for your patience as this work continues in your neighborhood.






Saturday, September 15, 2018


Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Phase 2 is paved out

M.A.R.S. Patching is completed

 
Work Anticipated to be performed, September 17th to September 21st.
  • Misc. clean up and punch lists



Thank You for your patience during this construction season.
 

Sunday, September 9, 2018



Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Phase 2 is paved out

M.A.R.S. Patching is completed

 
Work Anticipated to be performed, September 10th to September 14th
  • Misc. clean up and punch lists



Thank You for your patience during this construction season.
 

Friday, August 31, 2018



Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Paving on Various Phase 2 streets

·        Railroad is striped

 
Work Anticipated to be performed, September 4th to September 7th

·        Paving surface on all streets in Phase 2 completed
  • Mars program to tentatively completed

Thank You for your patience during this construction season.
We would like to take this opportunity to wish everyone a safe and happy Labor Day weekend




 
 

Friday, August 17, 2018

 
 



Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Milling has started in Phase 2

·        Sidewalk replacement as planned

 
Work Anticipated to be performed, August 13th to August 17th

·        Milling has begun on Railroad and will continue through the contract streets

·        Paving to start on Railroad and continue throughout the contract.

Friday, August 10, 2018


Group 1 Streets:

o   Magnolia Street

o   Timbers Edge Lane

o   Merle Lane

o   Blake Lane

o   Leanne Court

o   Sioux Trail

Work Performed:

·        Landscape restoration

·        Driveway restoration

 

Work Anticipated to be performed, August 13th to August 17th

·        Finish Landscape restoration

·              Finish Driveway restoration

 

Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Completed concrete curb & gutter replacement

·        Sidewalk replacement as planned

 
Work Anticipated to be performed, August 13th to August 17th

·        Start milling in Phase II beginning on Railroad

·        Paving in Phase II
 

Friday, August 3, 2018

Group II streets Milling and resurfacing


Group 1 Streets:

o   Magnolia Street

o   Timbers Edge Lane

o   Merle Lane

o   Blake Lane

o   Leanne Court

o   Sioux Trail

Work Performed:

·        Landscape restoration

·        Driveway restoration

 

Work Anticipated to be performed, August 13th to August 17th

·        Finish Landscape restoration

·              Finish Driveway restoration

 

Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Completed concrete curb & gutter replacement

·        Sidewalk replacement as planned

 
Work Anticipated to be performed, August 13th to August 17th

·        Start milling in Phase II beginning on Railroad

·        Paving in Phase II
 
  • Start Milling and paving in the M.A.R.S. program. Various throughout the Village.
 

Friday, July 27, 2018

Group 1 Streets: Milling On-Going and Paving to Begin. Group 2 Streets: Concrete Curb and Gutter Replacement Completed.

Group 1 Streets:
o   Magnolia Street
o   Timbers Edge Lane
o   Merle Lane
o   Blake Lane
o   Leanne Court
o   Sioux Trail

Work Performed:
·         Started pavement removal / milling of the existing asphalt pavement

Work Anticipated to be performed, July 30th to August 3rd
·         Complete pavement removal / milling of existing asphalt pavement
·         Roadway patching as needed
·         Pave new asphalt surface on roadway

Group 2  Streets:
o   Lakewood Lane (Greenwood Road to West End)
o   Prairie Lawn Road (Independence to Cul-de-Sac)
o   Pfingsten Road (Linneman Street to South End)
o   Jerrie Lane (Sherly Lane to Michael Manor)
o   Spruce Street (Robincrest Lane to Linneman Street)
o   Larkdale Drive (Spruce Street to 2121 Larkdale)
o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)
o   Railroad Avenue (Glenview Road to Linnman Street)

Work Performed:
·         Completed concrete curb & gutter replacement
·         Sidewalk replacement as planned

Work Anticipated to be performed, July 30th to August 3rd
·         Storm sewer improvements
·         Structure adjustments

Saturday, July 21, 2018

Concrete Curb and Gutter Replacement Continues. Milling to Begin

Work Performed:

·         Completed concrete curb & gutter replacement in Group 1
o   Magnolia Street
o   Timbers Edge Lane
o   Merle Lane
o   Blake Lane
o   Leanne Court
o   Sioux Trail
·         Performed concrete curb & gutter replacement along one side of the street in Group 2, including:
o   Lakewood Lane (Greenwood Road to West End)
o   Prairie Lawn Road (Independence to Cul-de-Sac)
o   Pfingsten Road (Linneman Street to South End)
o   Jerrie Lane (Sherly Lane to Michael Manor)
o   Spruce Street (Robincrest Lane to Linneman Street)
o   Larkdale Drive (Spruce Street to 2121 Larkdale)
o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)
o   Railroad Avenue (Glenview Road to Linnman Street)

Work Anticipated to be performed, July 23rd to July 27th  
·         Complete Concrete curb & gutter on opposite side of the street along Group 2 streets
·         Structure adjustments along Group 2 Streets
·         Pavement Removal / Milling along Group 1 Streets

Residents will be notified of any driveway restrictions within Group 2.

A majority of the concrete work will be completed next week within Group 2 streets. Work was performed on one side of the street last week, with the other side of the street being performed next week.

All the concrete work along Group 1 streets is now completed. We apologize for the delay, but needed to complete the storm sewer improvements prior to the remaining concrete work being completed. Pavement removal / surface grinding is anticipated to begin mid next week along Group 1 streets. If all goes as planned, asphalt surface paving will begin the week of July 30th

Thanks again for your patience as you are without driveway access during concrete curb & gutter removal and replacement.