Work Performed Last Week, June 4th to June 8th
o
Concrete curb & gutter replacement in the
following locations:
o Magnolia
Street
o Timbers
Edge Lane (north side of street only)
o Merle
Lane
o Blake
Lane (north side of the street only)
o Leanne
Court (east side of the street only)
o Sioux
Trail
Work Anticipated to be performed next week, June 11th
to June 15th
o
Complete concrete curb & gutter replacement
in the following locations:
o Timbers
Edge Lane (south side of street)
o Blake
Lane (south side of the street)
o Leanne
Court (west side of the street)
o
Begin storm sewer structure adjustments at the above
locations.
Thank you to all those residents that were without access to
their driveways while the concrete work was on-going. Typically, driveway
restricts will last 4-5 days while the curb is removed, forms installed,
concrete poured, and provide sufficient time to allow the concrete to cure.
Once the concrete and storm sewer work is completed, the
pavement resurfacing will begin. Additional information will be provided as
that work is scheduled to be performed.
You may not see activity on your street for periods of time.
Typically this is because the contractor is working in other parts of the
Village as part of the same contract. We
will do everything possible to ensure the time construction on each street is
minimized to the greatest extent possible.