Monday, June 18, 2018

Storm Sewer Improvements On-Going.

Work Performed Last Week, June 11th to June 15th  
o   Continued with concrete curb & gutter replacement in the following locations:
o   Magnolia Street
o   Timbers Edge Lane
o   Merle Lane
o   Blake Lane
o   Leanne Court
o   Sioux Trail
o   Adjusted structures in the curb line at the above locations.

Work Anticipated to be performed next week, June 18th to June 22nd  
o   Complete concrete curb & gutter and sidewalk replacement where gaps are left from manhole improvements
o   Storm Sewer installation along:
o   Timbers Edge Lane
o   Merle Lane

The contractor is currently working on completing the remaining concrete curb & gutter and sidewalk replacements along Group 1 (above list of streets) of the roadway improvements. We anticipate the storm sewer work and any remaining concrete sidewalk or curb & gutter replacement will be completed within the next 1 to 2 weeks

Once the concrete and storm sewer work is completed, the roadway resurfacing will begin.  We are hopeful that work will commence prior to the July 4th Holiday, but will heavily depend on weather conditions and work progress over the next few weeks.

Thanks again for all your patience as the remaining work is completed prior to asphalt resurfacing.