o
Continued with concrete curb & gutter
replacement in the following locations:
o Magnolia
Street
o Timbers
Edge Lane
o Merle
Lane
o Blake
Lane
o Leanne
Court
o Sioux
Trail
o
Adjusted
structures in the curb line at the above locations.
Work Anticipated to be performed next week, June 18th
to June 22nd
o
Complete concrete curb & gutter and sidewalk
replacement where gaps are left from manhole improvements
o
Storm Sewer installation along:
o Timbers Edge Lane
o Merle Lane
The contractor is currently working on completing the
remaining concrete curb & gutter and sidewalk replacements along Group 1 (above
list of streets) of the roadway improvements. We anticipate the storm sewer
work and any remaining concrete sidewalk or curb & gutter replacement will
be completed within the next 1 to 2 weeks
Once the concrete and storm sewer work is completed,
the roadway resurfacing will begin. We
are hopeful that work will commence prior to the July 4th Holiday,
but will heavily depend on weather conditions and work progress over the next
few weeks.
Thanks again for all your patience as the remaining work is
completed prior to asphalt resurfacing.