Friday, September 21, 2018

Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Phase 2 is paved out

M.A.R.S. Patching is completed

 
Work Anticipated the week of September 24th to the 28th.

  • Carol Lane to Begin with Curb Remove and Replace as well as storm sewer work.
Thank You for your patience as this work continues in your neighborhood.






Saturday, September 15, 2018


Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Phase 2 is paved out

M.A.R.S. Patching is completed

 
Work Anticipated to be performed, September 17th to September 21st.
  • Misc. clean up and punch lists



Thank You for your patience during this construction season.
 

Sunday, September 9, 2018



Group 2  Streets:

o   Lakewood Lane (Greenwood Road to West End)

o   Prairie Lawn Road (Independence to Cul-de-Sac)

o   Pfingsten Road (Linneman Street to South End)

o   Jerrie Lane (Sherly Lane to Michael Manor)

o   Spruce Street (Robincrest Lane to Linneman Street)

o   Larkdale Drive (Spruce Street to 2121 Larkdale)

o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)

o   Railroad Avenue (Glenview Road to Linneman Street)

 

Work Performed:

·        Phase 2 is paved out

M.A.R.S. Patching is completed

 
Work Anticipated to be performed, September 10th to September 14th
  • Misc. clean up and punch lists



Thank You for your patience during this construction season.