Friday, June 8, 2018

Concrete Curb and Gutter Replacements Started

Work Performed Last Week, June 4th to June 8th  
o   Concrete curb & gutter replacement in the following locations:
o   Magnolia Street
o   Timbers Edge Lane (north side of street only)
o   Merle Lane
o   Blake Lane (north side of the street only)
o   Leanne Court (east side of the street only)
o   Sioux Trail

Work Anticipated to be performed next week, June 11th to June 15th  
o   Complete concrete curb & gutter replacement in the following locations:
o   Timbers Edge Lane (south side of street)
o   Blake Lane (south side of the street)
o   Leanne Court (west side of the street)
o   Begin storm sewer structure adjustments at the above locations.

Thank you to all those residents that were without access to their driveways while the concrete work was on-going. Typically, driveway restricts will last 4-5 days while the curb is removed, forms installed, concrete poured, and provide sufficient time to allow the concrete to cure.

Once the concrete and storm sewer work is completed, the pavement resurfacing will begin. Additional information will be provided as that work is scheduled to be performed.

You may not see activity on your street for periods of time. Typically this is because the contractor is working in other parts of the Village as part of the same contract.  We will do everything possible to ensure the time construction on each street is minimized to the greatest extent possible.