Group 1 Streets:
o   Magnolia
Street
o   Timbers
Edge Lane
o   Merle
Lane
o   Blake
Lane
o   Leanne
Court
o   Sioux
Trail
Work Performed:
·       
Landscape restoration
·       
Driveway restoration
Work Anticipated to be performed, August 13th
to August 17th
·       
Finish Landscape restoration
·              Finish Driveway restoration
Group 2  Streets:
o   Lakewood
Lane (Greenwood Road to West End)
o   Prairie
Lawn Road (Independence to Cul-de-Sac)
o   Pfingsten
Road (Linneman Street to South End)
o   Jerrie
Lane (Sherly Lane to Michael Manor)
o   Spruce
Street (Robincrest Lane to Linneman Street)
o   Larkdale
Drive (Spruce Street to 2121 Larkdale)
o   Linden
Leaf Drive (Glenview Road to Roosevelt Avenue)
o   Railroad
Avenue (Glenview Road to Linneman Street)
Work Performed: 
·       
Completed concrete curb & gutter replacement
·       
Sidewalk replacement as planned
·       
Start milling in Phase II beginning on Railroad
·       
Paving in Phase II
- Start Milling and paving in the M.A.R.S. program. Various throughout the Village.