Group 1 Streets: Milling On-Going and Paving to Begin. Group 2 Streets: Concrete Curb and Gutter Replacement Completed.

Group 1 Streets:
o   Magnolia Street
o   Timbers Edge Lane
o   Merle Lane
o   Blake Lane
o   Leanne Court
o   Sioux Trail

Work Performed:
·         Started pavement removal / milling of the existing asphalt pavement

Work Anticipated to be performed, July 30th to August 3rd
·         Complete pavement removal / milling of existing asphalt pavement
·         Roadway patching as needed
·         Pave new asphalt surface on roadway

Group 2  Streets:
o   Lakewood Lane (Greenwood Road to West End)
o   Prairie Lawn Road (Independence to Cul-de-Sac)
o   Pfingsten Road (Linneman Street to South End)
o   Jerrie Lane (Sherly Lane to Michael Manor)
o   Spruce Street (Robincrest Lane to Linneman Street)
o   Larkdale Drive (Spruce Street to 2121 Larkdale)
o   Linden Leaf Drive (Glenview Road to Roosevelt Avenue)
o   Railroad Avenue (Glenview Road to Linnman Street)

Work Performed:
·         Completed concrete curb & gutter replacement
·         Sidewalk replacement as planned

Work Anticipated to be performed, July 30th to August 3rd
·         Storm sewer improvements
·         Structure adjustments